About the Project

The Central Plant is strategically located in downtown Houston between two Harris County and one State of Texas jail. The new facility supplements the existing plant which is at capacity and serves future growth as well as providing support to current buildings. The project also includes the construction of hot water/chilled water distribution piping installed approximately 30 feet under the street level to serve the three adjacent jail facilities.

The plant houses six 1,550-ton water cooled centrifugal chillers, chilled water and condenser water vertical in-line pumps, chemical treatment equipment, and a triplex water softener. A control room with a view of the chiller room area is located on the ground level. A second level houses the main switchgear, two 26.8 million Btuh and one 5 million Btuh fire tube boilers, three vertical in-line hot water pumps, expansion tanks, and side stream filter. The upper level also creates space for storage and expansion.

The Numbers

  • 28,000 sq ft

    Sq Ft
  • 14 Months

    Duration

The Details

Type: New Construction
Components: Central Plant
Method: Construction Manager at Risk
Client: Harris County

Technology Fact

Tellepsen builds lasting relationships with trade partners who have a similar vision of technology and innovation. We work closely with those partners who understand the importance of investing in research and development of better operational processes, such as BIM, pre-fabrication, and wearables that can improve safety, productivity, accuracy, and efficiency.

Partners

  • MEP Engineer: Jacobs Engineering

Similar Projects

Ask for the team that starts
with T.

Tellepsen is a family of companies with expertise in commercial, industrial, interior, concrete and other services.