About the Project

The new 150,000-square-foot elementary school was constructed on an occupied campus. The project was completed 64 days ahead of schedule despite 37 days of rain delays. The new buildings were constructed and the existing school demolished in 10 months with no disruption to the ongoing academic program. The building received LEED Silver Certification for excellence in sustainable design and construction. Through efficient teamwork and meticulous attention to detail Piney Point Elementary received the distinction of being the only newly constructed school in the HISD Bond Program to be completed prior to the start of the target school year.

The Numbers

  • 150,000

    Sq Ft
  • 10 months

    Duration

The Details

Type: New Construction
Components: Library, Occupied Campus, Site Work, Classrooms
Method: Construction Manager at Risk
Client: Houston Independent School District

Technology Fact

For well over a decade, Tellepsen has put processes in place to be digital and significantly reduce the use of paper-based processes that are often inefficient, costly, and inaccurate. By implementing these tools, we can provide a better experience for our employees, subcontractors, and customers.

Partners

  • Architect: VLK Architects
  • MEP Engineer: KME Engineering Consultants
  • Structural Engineer: Matrix Structural Engineers
  • Civil Engineer: Kelly R. Kaluza & Associates