About the Project
Tellepsen was awarded the Gas Process Facility job in Fort Stockton, Texas. With a peak of 800 workers on site, this West Texas location allowed us to bring together many skilled workers in one site. Planning and a disciplined schedule were keys to the success of this 16-month project.
This was considered a hybrid module construction which Included: 600,000 Civil/Structural; 1,700,000 Pipe/Mechanical; 300,000 Electrical; 127,000 Instrumentation; In-Line Instruments - 2,237 (EA); Pneumatic Tubing - 30,675 (LF); Instrument / Control Wire & Cable - 1,333,383 (LF); Cable Tray - 50,411 (LF)