About the Project

Build out of approximately 25,500 square feet of shell space on the 8th and 9th floor of the Health and Biomedical Science Building 2, which Tellepsen completed in late 2017. The space serves as an interim home for the newly chartered Medical School at the University of Houston until their new building is completed in several years. The Interim project was turned over in two phases; the first phase was completed October 2019 with the second phase completing January 2020. The project included classrooms, mock exam rooms and instruction laboratories, faculty offices, student lounge, study spaces, and a gross anatomy laboratory.

The Numbers

  • 25,500

    Sq Ft
  • 2

    Floors
  • 9 months

    Duration

The Details

Type: Build Out
Components: Classrooms, mock exam rooms, laboratories, offices
Method: Construction Manager at Risk
Client: University of Houston

Partners

  • Architect: Shepley Bulfinch Richardson and Abbott
  • MEP Engineer: E&C Engineers and Consultants Inc.

Similar Projects

Ask for the team that starts
with T.

Tellepsen is a family of companies with expertise in commercial, industrial, interior, concrete and other services.